After 14 months of construction, the intersection of Walker Road and Tecumseh Road will be fully reopened on Friday evening.
The infrastructure renewal project to install a new 1200mm Central Corridor Feedermain started in May 2024.
Construction crews are now in the final stages of the reconstruction. The project is expected to be complete by the end of the month.
The project also included upgrades to the road infrastrucure for smoother travel for all road users.